Agency-Level Bid Protests Under FAR 33.103: Rules and Deadlines

Federal contracting rules provide contractors with an avenue to dispute procurement errors directly with the contracting agency before or instead of turning to outside forums. Outlined under FAR 33.103 and rooted in Executive Order 12979, the agency protest system offers an administrative mechanism designed to resolve disputes within the buying agency itself. For construction bidders, understanding the specific procedures, required contents, and strict time windows governing agency protests is critical to protecting procurement rights.
Why File a Protest Directly With the Contracting Agency?
Under FAR 33.103, the stated policy is that agencies should provide for inexpensive, informal, procedurally simple, and expeditious resolution of protests. Agency procedures are intended to resolve challenges effectively, build confidence in the federal acquisition system, and reduce protests outside the agency. In resolving these matters, agencies may use alternative dispute resolution techniques, third-party neutrals, and personnel from other agencies where appropriate.
What Must Occur Before Submitting an Agency Protest?
Prior to the formal submission of an agency protest, all parties are required to use their best efforts to resolve concerns raised by an interested party at the contracting officer level through open and frank discussions. When those discussions do not resolve the matter, an interested party may file a formal protest addressed to the contracting officer or another official designated by the agency to receive protests.
What Information Must an Agency Protest Include?
Protests must be concise and logically presented to facilitate review by the agency. Failure to substantially comply with the required submission elements may result in dismissal. An agency protest must include:
- The name, address, and fax and telephone numbers of the protester.
- The solicitation or contract number.
- A detailed statement of the legal and factual grounds for the protest, including a description of resulting prejudice to the protester.
- Copies of relevant documents.
- A request for a ruling by the agency and a statement of the form of relief requested.
- All information establishing that the protester is an interested party for the purpose of filing a protest.
- All information establishing the timeliness of the filing.
What Are the Deadlines for Filing Under FAR 33.103?
Protest deadlines depend strictly on whether the challenge concerns the solicitation terms or post-solicitation events. Protests based on alleged apparent improprieties in a solicitation must be filed before bid opening or the closing date for receipt of proposals. In all other cases, protests must be filed no later than 10 days after the basis of protest is known or should have been known, whichever is earlier.
The agency may consider the merits of an untimely protest if good cause is shown or if the agency determines that the protest raises issues significant to its acquisition system. However, bidders must not assume late filings will be accepted.
How Does an Agency Protest Affect Award and Contract Performance?
If an agency receives a protest before contract award, the contract may not be awarded pending agency resolution, unless award is justified in writing for urgent and compelling reasons or determined in writing to be in the best interest of the Government. This justification or determination must be approved above the contracting officer level or by another official pursuant to agency procedures. When award is withheld, the contracting officer informs offerors who might become eligible and may request an extension of offer acceptance times.
For postaward protests, the contracting officer must immediately suspend contract performance if the protest is received within 10 days after contract award, or within 5 days after a debriefing date offered to the protester under a timely debriefing request in accordance with FAR 15.505 or 15.506, whichever is later. Performance remains suspended pending resolution within the agency, unless continued performance is approved in writing for urgent and compelling reasons or determined in writing to be in the Government's best interest.
Can You Request an Independent Review or Appeal to GAO?
Interested parties may request an independent review of their protest at a level above the contracting officer, as outlined in agency solicitations and procedures. Solicitations inform bidders whether this review operates as an alternative to consideration by the contracting officer or as an appeal of a contracting officer decision. Officials conducting the review need not be in the contracting officer supervisory chain and, when practicable, should have no personal involvement in the procurement.
However, pursuing an agency protest does not extend the deadline to obtain a stay at the Government Accountability Office. If an agency appellate review of a contracting officer decision occurs, it will not extend timeliness rules outside the agency. Any subsequent protest to GAO must be filed within 10 days of knowledge of initial adverse agency action. Contractors monitoring deadlines can review our guides on GAO bid protest deadlines and addressing federal bid mistakes.
How Quickly Must the Agency Issue a Decision?
Agencies are required to make their best efforts to resolve agency protests within 35 days after filing. Parties may exchange relevant information to the extent permitted by law and regulation. Final agency decisions must be well-reasoned, explain the agency position, and be delivered to the protester using a method that provides evidence of receipt.