Buy American on Federal Construction Bids: Domestic Content, the 20% Factor and How to Request an Exception
Photo: "Steel beams stacked beside a building in a construction yard" by Shixart1985, CC BY 2.0 (cropped).

Pricing a federal job with imported fixtures, panels or equipment can look cheaper on paper, until the Buy American rules change the math. Here's what the FAR clause says and where estimators get caught.

Key takeaways

What counts as domestic

FAR 52.225-9, Buy American - Construction Materials defines domestic construction material. For most manufactured items (not mainly iron or steel), the material must be made in the United States and "the cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029." Components of unknown origin "are treated as foreign." COTS items made in the U.S. also qualify.

For material that is "wholly or predominantly of iron or steel," it qualifies only if "the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components."

The exceptions

FAR 25.202, exceptions for construction material lets the contracting officer allow foreign construction material when:

The 20% evaluation factor

Under FAR 25.204, evaluating offers of foreign construction material, for material that isn't a critical item, "the contracting officer shall add to the offered price 20 percent of the cost of any foreign construction material proposed for exception" on unreasonable-cost grounds, unless the agency specifies a higher percentage. Critical items get an additional preference factor. In a tie, the offer without that excepted foreign material wins.

Estimator checklist

  1. Find the Buy American clause in the solicitation and any materials the Government already listed as excepted.
  2. Ask suppliers for domestic-content documentation on big-ticket manufactured items.
  3. If you plan to request an exception, include the information the clause requires (description, unit, quantity, price and more) with your offer.
  4. Price a domestic alternate so a denied request doesn't blow up your number.

Related: bid, performance and payment bonds and correcting bid mistakes.

General information, not legal advice. Check the solicitation for trade agreement clauses, which can change the rules. Sources: FAR 52.225-9, Buy American - Construction Materials; FAR 25.202, exceptions for construction material; FAR 25.204, evaluating offers of foreign construction material.