FAR 46.407: How the Government Handles Defective Work

By QuickBidSetup Editorial Team · Published October 31, 2026 · Sources linked below

FAR 46.407: How the Government Handles Defective Work
Photo: "Site Inspection (8546435)" by U.S. Navy photo by Petty Officer 2nd Class Henry Liu, Public domain, via Wikimedia Commons (cropped).

When trade contractors and estimators prepare proposals for federal projects, understanding quality control and delivery expectations is vital. Under federal procurement rules, defective or nonconforming deliverables are governed by specific administrative procedures. Here is a practical breakdown of how contracting officers evaluate, reject, or conditionally accept work that fails to meet specifications.

What Is the Government's Baseline Policy on Nonconforming Work?

Under FAR 46.407(a), the general policy is straightforward: a contracting officer should reject supplies or services that do not conform in all respects to contract requirements, referencing FAR 46.102. The government expects strict compliance with specifications. Deviating from this rejection policy is only permitted when acceptance is found to be in the government's interest, and any such acceptance must follow the specific authorization outlined in the regulation.

When Must the Contracting Officer Allow You to Fix Deficiencies?

If work falls short, does a contractor get an opportunity to correct it? Under FAR 46.407(b), the contracting officer ordinarily must give the contractor an opportunity to correct or replace nonconforming supplies or services, provided this can be completed within the required delivery schedule.

Several operational rules govern this opportunity:

Can the Government Ever Accept Work With Major or Critical Flaws?

When correction within the delivery schedule is not possible, the contracting officer ordinarily must reject supplies or services if the nonconformance is critical or major, or if the work is otherwise incomplete. However, under FAR 46.407(c), circumstances such as economy or urgency may lead the contracting officer to determine that acceptance or conditional acceptance serves the best interest of the government.

To make this formal determination, the contracting officer must base the decision upon five specific written inputs:

The contract administration office or directly involved government activity must furnish these data points in writing (or orally in urgent cases, followed by written confirmation). In addition, the contracting officer must obtain concurrence from the technical activity responsible for contract requirements and, where health factors are involved, from the agency's responsible health official.

How Are Minor Nonconformances and Review Groups Handled?

When issues are classified as minor nonconformances, FAR 46.407(d) provides an alternative administrative pathway. The cognizant contract administration office may make the determination to accept or reject the items, unless that specific authority is withheld by the contracting office of the contracting activity.

To assist in reaching that determination, the contract administration office is permitted to establish a joint contractor-contract administrative office review group. However, FAR 46.407 explicitly limits the authority of this group: accepting supplies or services that have critical or major nonconformances is strictly outside the scope of the review group.

What Price Adjustments and Withholdings Apply When Defective Work Is Accepted?

Accepting nonconforming work does not mean the government pays full price. Under FAR 46.407(f), clear financial consequences apply:

Why Are Prompt Written Rejection Notices Legally Critical?

When the government rejects work, timing and formal documentation are legally essential under FAR 46.407(g). Notices of rejection must state the reasons for rejection and be furnished promptly to the contractor. Promptness is critical because if timely notice of the nature of rejection is not provided, acceptance may in certain cases be implied as a matter of law.

Furthermore, the rejection notice must be issued in writing if:

  1. The supplies or services have been rejected at a place other than the contractor's plant;
  2. The contractor persists in offering nonconforming supplies or services for acceptance; or
  3. Delivery or performance was late without excusable cause.

Additionally, under FAR 46.407(h), the contracting officer must provide disposition instructions for counterfeit or suspect counterfeit items in accordance with agency policy, which may include directing the contractor to retain the items for investigative or evidentiary purposes. Understanding these quality rules helps contractors comply with related clauses such as FAR 52.246-12.