FAR 52.211-13 and FAR 52.242-14: Key Bidding Requirements

By QuickBidSetup Editorial Team · Published October 29, 2026 · Sources linked below

FAR 52.211-13 and FAR 52.242-14: Key Bidding Requirements

Federal construction jobs expose general contractors and trade subcontractors to strict schedule obligations and administrative delays. Understanding how federal contracts handle schedule adjustments and owner-directed pauses is essential when building estimates. Two critical contract clauses establish the baseline rules for schedule relief and delay expense recovery: FAR 52.211-13 Time Extensions and FAR 52.242-14 Suspension of Work. Here is a breakdown of their key requirements and how they affect your bid planning.

FAR 52.211-13: Element-by-Element Schedule Adjustments

When changes occur on a federal site, schedule relief is not automatically applied across the entire contract. Under Acquisition.GOV FAR 52.211-13, time extensions for contract modifications depend strictly on the extent to which revisions delay completion of specific construction elements. Federal contracting officers have clear contractual authority to limit calendar adjustments:

For framing, drywall, and interior subcontractors, this element-specific structure means that a delay on one floor or partition type will not necessarily postpone contract milestones elsewhere on the project. When budgeting or pricing change orders, estimators must track production by specific building elements rather than assuming a site-wide extension.

Liquidated Damages Adjustments Under Changed Schedules

A central protection in the time extensions clause is the provision addressing liquidated damages. When a contract change alters performance timelines, the resulting modification may revise the schedule alongside an equitable readjustment of liquidated damages under the new completion dates. Contractors facing altered milestones must ensure that the change documentation formally recalibrates these assessment benchmarks. This ensures that trades working under adjusted delivery schedules do not face penalties established under the original baseline dates, coordinating closely with related provisions such as FAR 52.211-12.

FAR 52.242-14: Government-Directed Suspensions

While FAR 52.211-13 addresses schedule revisions caused by modifications, FAR 52.242-14 governs administrative delays and interruptions ordered by the federal customer. The clause applies to solicitations and contracts when fixed-price construction or architect-engineer agreements are contemplated. Under paragraph (a), the Contracting Officer holds the contractual right to order the contractor in writing to suspend, delay, or interrupt all or any portion of the work. The government may issue such an order for whatever duration the Contracting Officer deems appropriate for the convenience of the Government.

Cost Adjustment Rules: Recovering Performance Expenses Excluding Profit

When jobsite operations are delayed, contractors face mounting standby expenses. FAR 52.242-14 establishes clear requirements for monetary adjustments when performance is interrupted for an unreasonable duration. To qualify for a cost adjustment under paragraph (b), the interruption must stem from one of two specific government actions:

If an unreasonable interruption meets these criteria, the contract must be modified in writing to grant an adjustment for any increased performance costs necessarily caused by the event. However, estimators and project managers must note a major restriction: this cost adjustment explicitly excludes profit. In addition, no adjustment is granted if performance would have been delayed by any other factor, including the negligence or fault of the contractor, or if another clause provides or excludes relief.

Strict Notice Deadlines: The 20-Day Threshold

Cost recovery under the suspension clause depends on following strict administrative procedures outlined in paragraph (c). Missing these procedural benchmarks can eliminate an otherwise valid claim:

Sources

Contract requirements and statutory clauses cited above are sourced directly from official federal acquisition regulations: