Price escalation clauses: how to protect your bid from material price swings

Price Escalation Clauses: How to Protect Your Bid From Material Price Swings
Photo: "US Navy 090527-N-8547M-107 Construction Electrician 3rd Class Olatunde Lawal, as" by U.S. Navy Photo by Mass Communication Specialist 2nd Class P, PUBLIC DOMAIN (cropped).

A bid priced in October might not be built until spring. If steel studs, drywall or copper jump in between, a fixed price can turn a profitable job into a loss. An escalation clause is the contract tool that shares that risk, and it only works if it's in the contract before you sign.

Key takeaways

What the federal model says

The federal government's labor-and-material escalation clause, FAR 52.216-4, Economic Price Adjustment, Labor and Material, is a good template for how these clauses are structured:

The broader rule, FAR 16.203-1, Fixed-price contracts with economic price adjustment, describes three types of adjustment: based on established (published) prices, based on actual costs of labor or material the contractor experiences, or based on cost indexes specifically identified in the contract.

Writing an escalation clarification on a private bid

Most subcontracts won't include an escalation clause unless you ask for one. A clarification in your proposal can start the conversation (see bid exclusions and clarifications). Make it specific:

  1. Name the materials covered (for example: steel studs and track, gypsum board, ceiling grid).
  2. Set the baseline: your supplier quote date and price, attached to the bid.
  3. Pick the measure: a supplier price letter or a named public index.
  4. Set a trigger so small swings don't create paperwork.
  5. Make it two-way: offering to pass along decreases makes the clause much easier for a GC or owner to accept.
  6. Set notice timing and the documentation you'll provide.
Sample wording: "Material pricing is based on supplier quotes dated [date] (attached). If the delivered cost of [materials] changes by more than [x]% from these quotes before purchase, the contract price will be adjusted up or down by the documented difference. Notice and supporting invoices will be provided within [x] days."

Other ways to limit the risk

Contract type matters too; see lump sum vs. unit price vs. cost-plus.

This is general information, not legal advice. Contract terms vary; have a construction attorney review anything you are unsure about before you sign.