FAR 22.406-2 Davis-Bacon Wages, Fringe Benefits, and Overtime Guide

Federal construction solicitations require trade contractors to price labor according to prevailing wage determinations. When bidding on covered federal work, estimators cannot simply carry standard payroll rates; they must structure bids around the wage and benefit rules outlined in FAR 22.406-2. Understanding how the Federal Acquisition Regulation distinguishes between basic cash wages, bona fide fringe benefit plans, and overtime computations is critical for pricing drywall, framing, and interior packages accurately without risking post-award compliance penalties.

Wage Composition: Allowable Payments vs. Excluded Costs

Under federal procurement regulations, a contractor computing wages paid to a laborer or mechanic can only include specific cost elements. According to FAR 22.406-2, allowable items consist of:

Crucially, contributions required by federal, state, or local laws cannot be counted toward the contractor's prevailing wage obligation. When estimators establish a trade crew's labor burden rate, mandated payroll taxes or statutory programs cannot be credited as bona fide fringe benefits under the wage determination.

Payment Methods Compared: All-Cash vs. Bona Fide Benefit Plans

Under FAR clause 52.222-6 (Construction Wage Rate Requirements), contractors have flexibility in how they satisfy their total wage obligation. Estimators can compare two primary fulfillment structures:

Option 1: Cash Equivalents Paid on Payroll. A contractor can pay the entire prevailing wage obligation as cash. In this model, the basic hourly rate and the hourly fringe benefit rate prescribed in the wage determination are combined and disbursed directly on the worker's paycheck. This approach provides simplicity on certified payroll reports but increases the cash outlay subject to direct payroll accounting.

Option 2: Bona Fide Plan Contributions or Combined Packages. Alternatively, a contractor may satisfy the requirement through any combination of cash wages and bona fide fringe benefit contributions, provided the total cost is not less than the sum of the basic hourly rate and fringe payments specified for the trade classification. Bidders carrying established company benefit programs can credit those third-party payments against the published fringe requirement.

Converting Benefits into Hourly Cash Equivalents

When fringe benefits or employer contributions are not stated as exact hourly cash figures, estimators and payroll managers must convert them into an hourly cash equivalent. FAR 22.406-2 establishes that the hourly equivalent is calculated by dividing the employer's contributions or costs by the employee's hours worked during the period covered by those payments.

The regulation outlines two distinct mathematical scenarios:

Overtime Calculations: Base Rates vs. Fringe Exclusions

Overtime estimating on federal projects requires strict separation between base wages and fringe credits. FAR 22.406-2 specifies that required overtime payments must be computed at not less than 1 1/2 times the basic hourly rate of pay.

When computing overtime premiums, estimators must apply the following structural rules:

In practice, the 1 1/2 multiplier applies strictly to the base rate. Fringe benefit amounts—whether paid into an irrevocable trust or disbursed as cash equivalents—remain payable at their straight-time hourly rate for all hours worked, unless a higher cash base rate is actively paid.

Resolving Equivalent Value Disputes with the Contracting Officer

If the contractor, the contracting officer, and the employees or their representatives cannot agree on the calculated cash equivalent of a benefit plan, the contracting officer must submit the issue to the Department of Labor for a final determination. Agency procedures dictate that this submission must include a detailed comparison of the payments, contributions, or costs in the wage determination against those proposed by the contractor, accompanied by the contracting officer's official comments and recommendations.