Labor burden: how to calculate your true hourly labor cost

Labor Burden: How to Calculate Your True Hourly Labor Cost
Photo: "Construction Worker, Amsterdam" by mbrochh, BY-SA 2.0 (cropped).

If you bid labor at the wage you pay, you're losing money on every hour. On top of wages, employers pay payroll taxes, insurance, benefits and paid time off. Together these are called labor burden.

Key takeaways

What goes into labor burden

For context on how big benefits are relative to wages nationally, see the BLS Employer Costs for Employee Compensation survey.

A worked example (illustrative numbers)

ItemPer year
Wages: $30/hr x 2,080 paid hours$62,400
FICA 7.65%$4,774
Unemployment taxes (example)$600
Workers' comp (example rate)$4,500
Health and retirement (example)$9,000
Total cost$81,274

If 10 days of holidays and vacation plus about 80 hours of shop and training time are paid but not billable, billable hours are about 2,080 - 80 - 80 = 1,920. Burdened cost = $81,274 / 1,920 = about $42.33 per billable hour, roughly 41% above the $30 wage. Your own numbers will differ; use your actual rates.

Using it in your bids

  1. Price labor at the burdened rate, not the wage.
  2. Then add overhead and profit on top. See markup vs. margin.
  3. Keep separate rates for crews with different classifications (workers' comp codes differ).

Related: bid-day checklist.