FAR 52.236-15 Bidding Checklist: Construction Contract Schedules
Photo: "Construction site @ 4161 W Hillsboro Blvd, Coconut Creek, FL (0)" by FunctioningMemberOfSociety, CC BY 4.0, via Wikimedia Commons (cropped).

Federal solicitations incorporate strict standard clauses that define project milestones, administrative submittals, and performance liabilities. For commercial drywall, framing, and interior subcontractors as well as prime contractors assembling estimates, understanding the clause prescribed in FAR 36.515—titled FAR 52.236-15 Schedules for Construction Contracts—is essential. Below is a structured bid-day checklist outlining the exact administrative mandates, reporting steps, and cost-bearing recovery mechanisms governed by this provision.

Checklist Item 1: Prepare for the Five-Day Submittal Window

Under paragraph (a) of the clause, the baseline deadline to produce your baseline plan is extraordinarily tight. Estimators and project teams must verify that the administrative team can deliver the initial documentation immediately after mobilization begins:

Checklist Item 2: Map Salient Features, Materials, and Plant

The clause explicitly outlines the required content of the schedule chart. It cannot merely depict high-level trade handover dates; it must show the detailed sequence of operations. When building your estimate, account for the management time needed to document:

Because procuring plant and specialty assemblies must be accounted for on the chart, teams should verify these schedule-building expenses under Estimating General Conditions: The Job Costs That Aren't in Your Takeoff before submitting a final number on bid day.

Checklist Item 3: Track and Deliver Annotated Progress Updates

Schedule compliance under FAR 52.236-15 does not end with baseline approval. Paragraph (b) requires active, ongoing maintenance of the progress chart:

Estimators should confirm that supervisory staff have the capacity to log progress and issue the three physical copies whenever directed, preventing administrative noncompliance.

Checklist Item 4: Price the Risk of Directed Acceleration Without Government Cost

One of the most critical risk items in the clause is the financial exposure that arises if field progress falls behind. If, in the opinion of the Contracting Officer, work drops behind the approved chart, the contractor is obligated to take steps necessary to improve progress without additional cost to the Government.

Under these circumstances, the Contracting Officer possesses the authority to direct specific remedial actions at the contractor's own expense, including:

Because these measures cannot be billed to the Government as contract extras, bid pricing must accurately reflect crew sizing and production assumptions to avoid uncompensated acceleration orders.

Checklist Item 5: Protect Against Default Termination

Paragraph (c) establishes severe contractual consequences for noncompliance. If a contractor fails to adhere to the requirements of the Contracting Officer under this clause, that failure serves as grounds for a formal determination that the contractor is not prosecuting the work with sufficient diligence to complete the project on time.

Upon issuing that determination, the Contracting Officer may terminate the contractor's right to proceed with the entire project or any separable part of the work, in accordance with the contract default terms. Checking schedule feasibility prior to bid submission is the contractor's primary defense against a diligence default.

Sources

52.236-15 Schedules for Construction Contracts. | Acquisition.GOV

Published October 28, 2026. No affiliate links on this page. Facts come from the sources linked above; check them for updates.