Gaskets, Packing, and Sealing Devices Price Trends: BLS PPI Data for Mechanical Bids

By QuickBidSetup Editorial Team · Published November 9, 2026 · Sources linked below

Gasket and Sealing Device PPI Trends: Mechanical Bids
Photo: "Conflat Flange" by Kkmurray, CC BY-SA 3.0, via Wikimedia Commons (cropped).

Estimators pricing mechanical packages, piping tie-ins, and industrial equipment assemblies must evaluate the rising baseline of joint accessories. The U.S. Bureau of Labor Statistics PPI commodity data for series WPU1398 provides an objective measure for Tracking gaskets, packing, and sealing devices. This quick-reference explainer details current price trends, multi-year shifts, and key figures to help contractors maintain accurate cost allowances.

PPI Benchmark Summary for Mechanical Bidders

Producer price data for nonmetallic mineral products under commodity code WPU1398 uses December 1985 = 100 as its index base period. The series is not seasonally adjusted, and recent monthly releases remain preliminary and subject to revision for four months following initial publication. The benchmark points below establish where the market sits relative to historical project intervals.

U.S. Bureau of Labor Statistics Series WPU1398: Gaskets, Packing, and Sealing Devices
Period Index Level Change to Latest (September 2026)
Latest (September 2026) 287.6 (raw 287.565) +0.0%
One Year Earlier (September 2025) 266.6 (raw 266.600) +7.9%
Two Years Earlier (September 2024) 252.2 (raw 252.161) +14.0%
Five Years Earlier (September 2021) 215.6 (raw 215.599) +33.4%
Pre-Pandemic Baseline (January 2020) 202.9 (raw 202.900) +41.7%
Window High (September 2026) 287.6 (raw 287.565) +0.0%

Multi-Year Escalation and Historical Milestones

A review of historical data from January 2019 to September 2026 demonstrates sustained upward pressure on sealing materials. The lowest monthly value recorded in this period was 200.3 (raw 200.300) in May 2019. By contrast, the highest monthly value occurred in September 2026 at 287.6, meaning the market is currently operating at its peak pricing level.

Annual averages calculated from monthly index values illustrate the year-over-year progression:

Compared to January 2020, sealing devices have escalated by +41.7%. When evaluated against five years earlier in September 2021, costs are up +33.4%, and prices have increased +14.0% relative to September 2024. Estimators bidding jobs tied to older project baselines must adjust unit rates accordingly.

Thirteen-Month Price Trend Breakdown

Short-term price shifts across the trailing 13 months highlight consistent incremental gains rather than wild fluctuations. In September 2025, the index stood at 266.6. It stepped up to 274.0 in October 2025, followed by 274.5 in November 2025 and 274.9 in December 2025.

The index advanced further at the start of 2026, recording 280.5 in January 2026, holding flat at 280.5 in February 2026, and moving to 280.6 in March 2026. The spring brought another leg upward, with April 2026 at 283.7, May 2026 at 284.2, and June 2026 at 285.9. Across the late summer, July 2026 reached 286.3 and remained at 286.3 in August 2026 before rising to 287.6 in September 2026. This reflects a month-over-month increase of +0.4% from August 2026 to September 2026, completing a +7.9% rise over the 12-month span.

Bidding Strategies for Trade Contractors

Because gaskets, packing, and seals accompany major equipment, valves, and piping connections, estimators should coordinate component pricing alongside related trades. Consider these practical estimating safeguards:

Sources

Commodity price movements and baseline figures cited above are drawn from the U.S. Bureau of Labor Statistics Gaskets, Packing, and Sealing Devices PPI Data (Series WPU1398).

Published November 9, 2026. No affiliate links on this page. Facts come from the sources linked above; check them for updates.