Metal stud framing takeoff: studs, track, openings and gauges

Interior non-structural steel framing is usually specified to ASTM C645 (the member standard) and installed per ASTM C754. The takeoff itself is simple once you are consistent. The mistakes come from skipping openings, corners and height changes.

1. Organize by wall type

Group walls by type from the partition schedule: stud size, gauge, spacing, height and board layers. Take off linear feet (LF) of each type separately. A 3-5/8" stud at 16" o.c. and a 6" stud at 24" o.c. are different line items.

2. Studs from spacing

Basic count per wall = (wall length in inches ÷ spacing) + 1. Then add:

3. Track

Top and bottom track = 2 × wall LF, plus header and sill track at openings. Deflection (slip) track at the structure counts as its own line item and costs more.

4. Stud length

Studs come in stock lengths, and long walls may need splices or longer special-order material. Note heights above the ceiling to the deck. Walls that go full height to the structure use much more material than walls that stop just above the ceiling.

5. Gauge and height

Allowable height depends on stud depth, gauge, spacing, board layers and the design lateral load. Use the manufacturer's published limiting-height tables for the specified product. Don't guess.

6. Don't forget